Project Details

Ultra-Pure Water (UPW) Project

What We Did

A focused 5-month project delivering ultra-pure water infrastructure through prefabricated piping and high-precision offsite welding, enabling rapid installation and reliable handover.

 

  • Installed prefabricated PVDP piping (up to 200mm).
  • Fabricated and installed carbon and stainless-steel pipework.
  • Managed peak workforce of 40 trades.
  • Delivered 4,366 weld inches, with 86% offsite completion.
  • Completed full testing and handover.