Project Details

Industrial tower beside large factory building

What We Did

BMD executed the full mechanical and structural installation scope, delivering precision fabrication and assembly works across piping systems and auxiliary steel structures within the HRSG unit.

  • Fabrication and installation of approximately 110 tonnes of large and small bore piping
  • Installation of heavy wall carbon steel and chrome piping in P11, P22, and P91 grades
  • Fabrication and installation of auxiliary steelwork, including platforms, ladders, and stairs
  • Completion of HRSG supporting lattice framework and distribution grid baffle system using grade 316Ti and 321 materials
  • Execution of repair works to support ongoing HRSG maintenance and operational reliability